All articles

After-Impact Inspections: The Procedure Every Site Needs

Rackstor UK Ltd

Why after-impact inspection is a separate duty

Weekly checks and annual expert inspections are scheduled activities. An impact is an event, and PUWER 1998 treats events differently: regulation 6 requires inspection not only at suitable intervals but also each time exceptional circumstances liable to jeopardise the safety of the equipment have occurred. A forklift or reach truck striking a loaded rack is exactly that.

HSE guidance HSG76 and BS EN 15635 both make the practical expectation explicit: racking that has been struck should be assessed before it is put back into normal service. It does not matter that the annual inspection was three weeks ago. The inspection interval is irrelevant to an event that has already happened.

This is why sites need a written procedure rather than good intentions. Impacts happen at inconvenient times, often on shifts with fewer supervisors, and the decision about whether to reload a bay should never rest on how busy the operation is that afternoon.

Why light impacts are not trivial

Racking is an efficient structure, which is another way of saying it has very little spare material in it. An upright carries load through a thin cold-formed section whose strength depends on its geometry, so its capacity comes from being straight and undeformed. Deform the section and capacity drops, because a bent column carries load eccentrically and that eccentricity grows under load rather than resisting it.

That is why a dent that looks cosmetic can matter. The damage that concerns an inspector most is not always the largest — a sharp localised crease concentrates the loss of section far more than a gentle bow of the same amplitude, and creases are exactly what a hard, low-speed contact from a forklift mast or pallet corner produces.

The second reason is that racking is a connected system. A frame is shared between two bays; beams and bracing tie runs together. Weaken one frame and load redistributes into its neighbours, which may already be near their working load. That is the mechanism by which one damaged component becomes a progressive failure of a whole run rather than a local problem.

The third is cumulative damage. Steel does not recover. Three separate light contacts at the same position over a year are not three trivial events; they are one component that has been progressively degraded — which is precisely why green findings need recording by location rather than dismissing.

Step one: stop and offload

The moment an impact is identified, the affected bay comes out of use. Offload it — starting from the top level and working down — and do not place further pallets in it. If the impact was heavy enough that offloading itself looks risky, keep people out of the area and get competent advice before disturbing the load.

Consider the neighbours as well as the struck bay. Racking is a connected structure: a compromised frame is shared between two adjacent bays, and load redistributes through beams and bracing into the runs either side. If a frame is visibly displaced, treat the bays on both sides of it as suspect until they have been assessed.

Do not attempt to correct anything at this stage. Pushing a frame back with a forklift, tightening a sheared anchor, or refitting a distorted beam connector changes the evidence and can make an unsafe component look serviceable.

Step two: isolate and communicate

Physically isolate the bay so it cannot be reloaded by someone who has not heard about the impact. Barrier tape across the bay, a printed 'do not load' notice at the pick face, and where possible a physical barrier at floor level. On WMS-driven operations, block the locations in the system as well — verbal instructions do not survive a shift change, but a blocked location does.

Report the impact to the nominated Person Responsible for Racking Safety immediately. The report should record when it happened, which bay reference, what struck it and roughly where the contact was, plus the name of the driver or the person who found it. If the site has CCTV, note the time so footage can be retrieved before it is overwritten.

Reporting culture is the weak link here. Drivers who expect disciplinary consequences report fewer impacts, and the impacts that go unreported are the ones that carry load until the next expert inspection. Sites that fit continuous racking impact monitoring consistently find that recorded impacts exceed reported impacts, particularly outside day shift.

Step three: competent assessment

A trained PRRS assesses the struck bay against the BS EN 15635 tolerances, and refers to an expert inspector where the damage is beyond the limits of a site assessment. The assessment covers the front and rear faces of both frames, the full height of the uprights rather than just the height of the strike, the beams at every level and their end connectors, the safety clips, the horizontal and diagonal bracing, and the baseplates and floor fixings.

The things most often missed are worth listing. Damage above the point of impact, because energy travels up a frame. Rear-face damage where the truck reached through from the opposite aisle. Sheared or lifted floor anchors and hairline cracking in the slab around them, which are only visible if you look down. Bracing members knocked loose at the weld or bolt. Beam connectors pulled slightly out of the frame column, which can look almost normal but has compromised the connection carrying the load.

Assess by measurement, not by eye. Out-of-straightness is checked against a straight edge in both planes, and a sharp kink or crease is treated more seriously than a smooth bow of similar amplitude because it concentrates the loss of section. The full classification logic is set out in red, amber and green racking damage explained.

Step four: classify and act

Green risk: the damage measures within tolerance. The bay can return to service, but the location is recorded and added to the weekly inspection route so any progression is spotted. Repeat impacts at a green location still need investigating even though nothing needs replacing.

Amber risk: the component is outside tolerance but judged safe for continued short-term use. Plan and complete the replacement within the defined period, commonly four weeks, and monitor the location more closely in the meantime.

Red risk: the component cannot be relied on to carry load. The bay stays offloaded and isolated until the component has been replaced. Do not reload on the basis that the bay 'looks all right now'.

Where components need replacing, they are replaced — not straightened. Cold-straightening a yielded upright does not restore its capacity. Replacement parts must be compatible with the installed system, because racking systems are not interchangeable even where components physically fit. Our damage repair and replacement guidance covers the repair-versus-replace decision and how to document it.

When to call an expert inspector rather than assess in-house

A trained PRRS can handle most routine contacts, and a site that refers every scuff to an external inspector will end up referring nothing at all because the process becomes unworkable. The judgement is about where site competence genuinely stops.

Call an expert inspector where: a frame has visibly moved or is out of plumb; a floor fixing has failed or the slab is cracked around an anchor; damage is at a splice or at the base of a tall run; the damage is in drive-in, drive-through, double-deep, cantilever, mobile or pallet-live racking, where access and load paths make site judgement much harder; the impact involved injury, significant stock loss or an insurance claim; or you simply want an independent, documented opinion before reloading.

The same applies where the assessment is ambiguous. If two competent people on site disagree about whether a component is amber or red, that disagreement is itself the answer: keep the bay offloaded and get it assessed by an expert inspector.

The reporting problem behind most unsafe racking

Almost every warehouse with a damage problem also has a reporting problem. Impacts go unreported when drivers expect blame, when reporting takes too long, or when nothing visibly happens as a result. The impacts that go unreported are precisely the ones that keep carrying load until somebody notices months later.

The fix is partly cultural — make reporting quick, routine and blame-free, and be visibly seen to act on it — and partly structural. Mark bay references physically on the racking so a driver can report a location accurately in seconds without leaving the truck. Give the PRRS explicit authority to take a bay out of use on the spot without seeking approval. Record every impact and its outcome so the workforce can see the process working.

Where impacts recur in areas nobody observes, particularly on quieter shifts, continuous racking impact monitoring records each impact with its time, location and severity. That removes the reliance on self-reporting entirely and gives your inspector a genuine damage history to work from.

Step five: verify, sign off and reload

Once repair or replacement is complete, the work is verified before the bay returns to service: correct components fitted, bolts and anchors torqued and complete, safety clips in place, bracing reinstated, frame plumb and baseplate bearing properly on the slab. If the repair changed the configuration — a different beam section, or a beam level moved — the load notice for that run may no longer be correct and needs updating. See load notices and racking signage.

Sign the bay back into service in writing, naming who verified it and when, then unblock the locations in the WMS and remove the physical isolation. That final written step is what turns an incident into a closed record.

Keep the whole chain together: the impact report, the assessment with measurements and photographs, the classification, the repair record and the sign-off. That package is what demonstrates you inspected following exceptional circumstances and acted on the result — and it is what an insurer, an auditor or an HSE inspector will ask to see.

Turning incidents into prevention

Individual impacts are operational noise. Patterns are information. Plot impacts by location and by shift over a few months and the same handful of positions almost always dominate: aisle ends by the main traffic route, the first frame past a doorway, pick faces on a tight turning circle, columns beside a wrapping station.

Those patterns point at fixes that are cheaper than repeated frame replacement — end-of-run barriers and frame protection at the pinch points, changing the traffic direction, widening a specific aisle, relocating a fast-moving pick face away from a corner, or reviewing whether the MHE in use suits the aisle width.

Feed the same data into your annual expert inspection. An inspector who can see the impact history will tell you far more about your installation than one working from a single day's observation. Details of that inspection are on the annual SEMA-aligned inspection page, and the weekly regime that supports it is covered in PRRS training.

Frequently asked questions

Do we legally have to inspect racking after every impact?

PUWER 1998 regulation 6 requires inspection after exceptional circumstances liable to jeopardise the safety of work equipment, and an MHE strike on loaded racking is such a circumstance. HSG76 and BS EN 15635 both expect struck racking to be assessed before it returns to normal service, regardless of when the last scheduled inspection took place.

Can we reload the bay if there is no visible damage?

Only after a competent assessment concludes the damage is within tolerance. Impacts frequently cause damage that is not obvious from the picking face — above the strike point, on the rear face, at the beam connectors or at the floor fixings — so the check needs to be deliberate and measured rather than a glance.

Who can carry out the after-impact assessment?

A trained PRRS can assess most impacts against BS EN 15635 tolerances. Where damage is significant, ambiguous, structural, or involves a frame that has moved or a floor fixing that has failed, it should be referred to an expert inspector before the bay returns to service.

Should we always call out an inspector after an impact?

Not necessarily for every minor contact, provided you have a trained PRRS and a written procedure. You should call an inspector where the assessment is beyond site competence, where damage is red-rated, where a run has been displaced, or where you want an independent record because an injury, stock loss or insurance claim is involved.

Can a damaged upright be straightened rather than replaced?

No. Once the steel has yielded, straightening does not restore load capacity and may hide the extent of the damage. Damaged structural components should be replaced with parts compatible with the original racking system, fitted by competent installers.

What records should we keep for each impact?

The impact report with date, time, bay reference and what happened; the assessment with measurements and photographs; the classification; the repair or replacement record; and the written sign-off returning the bay to service. Keep them together so the whole sequence can be followed by someone who was not there.

Talk to a SEMA inspector

Get a same-day quote for a SEMA-aligned, SARI accredited pallet racking inspection at your site.

Our Brands

Rack Safety Inspections is part of the Rackstor Group of storage and warehouse specialists.